A little demo in the downstairs!
Big week! 200 Amp electrical service is installed. Inspector will be out Tuesday for final inspection and Eversource is going to do the final cutover on the street (likely upgrading the line). There ended up being 4 bad circuits in the house, all of which either needed new plugs, switches or wiring, resulting in the new style breakers constantly tripping. This has all been resolved. In prep for the HVAC system including new furnace, water heater, duct work, etc. I dissembled the majority of the “right bedroom” (maybe that’s what we’ll call it?). This involved taking the ceiling down, sheetrock, walls, door, etc. So much nicer looking now! Original: Cleaned Out!! Unfortunately found some old mold. Best guess is the water heater let go at some point and flooded downstairs. The basement itself seems pretty dry. This will all be ripped out in due time!